My LC PD is Jul 25, 2001. Pikachu or anyone do u have a rough estimate of how much longer it will take for approval going at this rate.

I also have a question regarding 140 once Labor is approved, do I get the same PD for 140 i.e. Jul 25 or is it after filing 140 I get another PD separately for 140. How much time for 140 from Vermont any idea?

Thanx in advance
Dinesh
 
Few of the cases coming out yesterday

Pikachu I hope yours is one of these...

Thanks a lot for your all your help to this Group.
This are some of the cases that approved yesterday.. there might be more than following cases

Case No Action RD
01308250 Certified -- FINAL ACTION On 12/27/2001. 04/09/2001
01308253 Certified -- FINAL ACTION On 12/27/2001. 04/09/2001
01307304 Certified -- FINAL ACTION On 12/27/2001 03/07/2001
01307307 Certified -- FINAL ACTION On 12/27/2001. RD 03/07/2001
01307317 Certified -- FINAL ACTION On 12/27/2001. 03/07/2001
01307493 Certified -- FINAL ACTION On 12/27/2001. 03/13/2001
01307494 Certified -- FINAL ACTION On 12/27/2001. 03/13/2001
01307512 Certified -- FINAL ACTION On 12/27/2001. 03/13/2001
01307582 Certified 03/14/2001
01307583 Notice of Findings Issued 03/14/2001
01307584 Certified -- FINAL ACTION On 12/27/2001. 03/14/2001
01307586 Certified -- FINAL ACTION On 12/27/2001. 03/14/2001
01307587 Certified -- FINAL ACTION On 12/27/2001. 03/14/2001
01307864 Certified -- FINAL ACTION On 12/27/2001. 03/22/2001
01307865 Certified -- FINAL ACTION On 12/27/2001. 03/22/2001
01307872 Certified -- FINAL ACTION On 12/27/2001. 03/22/2001
01307873 Certified -- FINAL ACTION On 12/27/2001. 03/22/2001
01307878 Certified -- FINAL ACTION On 12/27/2001. 03/22/2001
 
RI SESA contact info

how can i find out the status of my application in RI SESA? I heard RI SESA is processing 4/2000 now. Any personal experiences with RI SESA?
 
No Title

10..

1305394 Software Engineer 04-Jan-01 Certified -- FINAL ACTION On 12/31/2001.
1307297 Electronics Engineer 07-Mar-01 Certified -- FINAL ACTION On 12/31/2001.
1307318 Data Base Administrator 07-Mar-01 Certified -- FINAL ACTION On 12/31/2001.
1307374 Painter 08-Mar-01 Reduct. in Recruitment Denied On 12/31/2001.
1307375 Automobile Service Station Mechanic 08-Mar-01 Notice of Findings Issued -- FINAL ACTION Due On 0
1307378 Sausage Maker 08-Mar-01 Certified -- FINAL ACTION On 12/31/2001.
1307561 Software Engineer 14-Mar-01 Certified -- FINAL ACTION On 12/31/2001.
1307562 Systems Analyst 14-Mar-01 Certified -- FINAL ACTION On 12/31/2001.
1307563 Programmer Analyst 14-Mar-01 Certified -- FINAL ACTION On 12/31/2001.
1307564 Data Base Design Analyst 14-Mar-01 Certified -- FINAL ACTION On 12/31/2001.
 
Happy new year!!!!

I hope everyone of us will get LC approved within a reasonable waiting time in this year.
 
define reasonable....

thanks for your wishes, but what\'s reasonable?...I\'ve been waiting for a year now!
 
record

I have been in labor for 2.5 years. My job title is unique and was not in DOL\'s list of titles, got bumped twice, its the first case for the company slowing everything down, had crapy lawyers and so on......
Its too painful to even participate in these discussions and I have been silently listening, boy have I learnt what is patience.
My deepest regards to all who are supporting others.
My application date now is 4/11/01
 
2.5 years first time .... 1+ years second time....

although it was my fault for changing companies...hang in there bud
 
No Title

Here is a small report that I created.. Just a yr end summary !!

 
Year End Analysis for Boston Dol :
=====================================================================

No of cases received (2001):
=====================================================================
       Total Certified Received NOF.. 1st Case touched on..
Jan 537 470 4 63 16 July
Feb 523 446 23 54 4 Sept
March 943 402 426 115 13 Nov
April 757 269 374 114 7 Dec

Yr End Totals :
=====================================================================
Jan 4 - April 30 : 2760 cases received
       Certified : 1587
        Received : 827
Not Yet Certified : 346
                        |___ Breakup of 346 ___

                              3 Denied Permanent
                             49 Denied Temporary
                              7 NOF Rebuttal Received
                             15 NOF Time Extension Granted
                             83 NOF Issued
                            165 RIR Denied (3 Software Engineers)
                              4 Remand issued to state
                             16 Withdrawn

Monthly Breakups (for cases received in region from Jan 4 - April 30)
=====================================================================
July : 23 Aug : 118
Sept : 115 Oct : 187
Nov : 200 Dec : 164

Total from July 16 : 807 (for cases rd in DOL 1/4 - 4/30 2001)
=====================================================================
 
I CANNOT beleive this...

My script just stopped running this second..

This is it !!!!!!!!!!! 22 came out today with my # having the glorious CERTIFIED next to it !! Thanks to all of you, specially in limbo, markma, gc gc, seenoend, Mainer and all you others (i\'m forgetting names - my brain has blanked out with this \'rush\') for your steadfast support..

There IS light at the end of this tunnel.. Just hang in there..

1307348 Machine Shop Supervisor, Production 08-Mar-01 Certified -- FINAL ACTION On 01/02/2002.
1307367 Chief, Computer Programmer 08-Mar-01 Certified -- FINAL ACTION On 01/02/2002.
1307368 Construction Worker I 08-Mar-01 Notice of Findings Issued -- FINAL ACTION Due On 0
1307370 Secretary 08-Mar-01 Reduct. in Recruitment Denied On 01/02/2002.
1307371 House Worker, General 08-Mar-01 Certified -- FINAL ACTION On 01/02/2002.
1307373 Cook 08-Mar-01 Certified -- FINAL ACTION On 01/02/2002.
1307377 Canvas Worker 08-Mar-01 Certified -- FINAL ACTION On 01/02/2002.
1307379 Stonemason 08-Mar-01 Certified -- FINAL ACTION On 01/02/2002.
1307382 Secretary 08-Mar-01 Reduct. in Recruitment Denied On 01/02/2002.
1307384 Manager, Office 08-Mar-01 Certified -- FINAL ACTION On 01/02/2002.
1307385 Software Engineer 08-Mar-01 Notice of Findings Issued -- FINAL ACTION Due On 0
1307389 Data Base Administrator 09-Mar-01 Certified -- FINAL ACTION On 01/02/2002.
1307390 Vice President, Financial Institution 09-Mar-01 Certified -- FINAL ACTION On 01/02/2002.
1307391 Traffic Agent 09-Mar-01 Certified -- FINAL ACTION On 01/02/2002.
1307415 Manager, Operations 09-Mar-01 Certified -- FINAL ACTION On 01/02/2002.
1307416 Software Engineer 09-Mar-01 Certified -- FINAL ACTION On 01/02/2002.
1307417 Programmer Analyst 09-Mar-01 Certified -- FINAL ACTION On 01/02/2002.
1307418 Director, Research And Development 09-Mar-01 Certified -- FINAL ACTION On 01/02/2002.
1307419 Custom Tailor 09-Mar-01 Certified -- FINAL ACTION On 01/02/2002.
1307420 Roofer 09-Mar-01 Certified -- FINAL ACTION On 01/02/2002.
1307422 Manager, Computer Operations 09-Mar-01 Certified -- FINAL ACTION On 01/02/2002.
1307423 House Worker, General 09-Mar-01 Certified -- FINAL ACTION On 01/02/2002.

My PD was Nov 2000 with the CT SESA sending a salary RFE.. Forwarded to the DOL on Feb 8 2001 with RD March 9 2001 and AD Jan 2 2002. EEEEEEEEEEEEEEEHHHOOOOOOOOOOOOOOOOOO !!! Thanks Phonon.. This is a good way to begin the new year !
 
awriiight!!

See you soon in the I-140 queue dude...unless you get out of there before I make it there! Good luck dude

P.S. And you were worried mine would come before yours...
 
Wonderful news pichachu

GoodLuck!!! Thanks for all of your support you have provided to this board.

Goodluck Again!!!
 
Top