I-140 CALIFORNIA EB2 Tracker only

concurrent adjudication

desi145 said:
Its good to know that things are moving..at the same time..i really feel bad that mid-sept case gets approved in june and early-aug cases are still pending.

My RD is 8/8/2003.

I hope the CSC will start concurrently adjudicating I-140 and I-485 as instructed by the memo. this is equally as important.

Baywatcher.
 
What is the requirement to file(I140/I485) under the pilot project?

Hi All,

My LC certified on 25th of June 2004. I do not know What I need to communicate to my Attorney to do concurrent filing using the pilot project? My main question is hear that Do we have any option to select the choice to file under the pilot project (thru which they claims that INS complete the whole I140/I485 in 90 days) ? or INS decides this option?

FYI : My LC certified under EB2 category.

Thanks in advance for your replly...

kk007
 
kk007 said:
Hi All,

My LC certified on 25th of June 2004. I do not know What I need to communicate to my Attorney to do concurrent filing using the pilot project? My main question is hear that Do we have any option to select the choice to file under the pilot project (thru which they claims that INS complete the whole I140/I485 in 90 days) ? or INS decides this option?

INS Decides

FYI : My LC certified under EB2 category.

Thanks in advance for your replly...

kk007
 
Hi PhDChemist,
Can you please scan data for cases around 8th August'03. I know there are 4 employees at my workplace around the same dates and no status change after filed for any of these. So, just want to find out if they really touched any case with RD - 1st week of august?

my WAC03231XXX if that can help you. If It's too much for you, then please advise me how you scan and/or provide the script.

Thanks in advance,
 
desi145 said:
Hi PhDChemist,
Can you please scan data for cases around 8th August'03. I know there are 4 employees at my workplace around the same dates and no status change after filed for any of these. So, just want to find out if they really touched any case with RD - 1st week of august?

my WAC03231XXX if that can help you. If It's too much for you, then please advise me how you scan and/or provide the script.

Thanks in advance,

Hi desi145,

I sent you a private message. Check it out.
 
Yes, the message on my I-140 has changed too, 270 to 300 days.
What kind of days are they talking about?
They received my case on Aug 20, 2003 plus 300 days it's June 15th. Or maybe they use a lunar calendar as they are in the cosmos. :p
 
Welcome Back T3k

Thanks for posting the LC status last year!

Good luck to us all on this thread.

Baywatcher
concurrent I-140/I-485 RD 9/12/03
 
As I know, that's work-days, not Calendar day.
300*7/5= 420 calendar days
270*7/5 = 378 calendar days
So,
... it's about one year and one/two months as they announce.


toy3kin192 said:
Yes, the message on my I-140 has changed too, 270 to 300 days.
What kind of days are they talking about?
They received my case on Aug 20, 2003 plus 300 days it's June 15th. Or maybe they use a lunar calendar as they are in the cosmos. :p
 
new processing JIT

same old ..no movement for EB2..processing times just arrived.
looks like fastest 140 for unskilled professional. does it mean BCIS prefers unskilled over skilled person? or they just reject 140 for all unskilled..that's why it's fastest?
 
MY ANSWERS IN CAPITAL LETTERS.

Recently I 140 and I 485, EAD and AP have been applied concurrently in EB2 category.
What things do we need to track the GC process from now on.
I am assuming RD is the received date of all the above four applications.
I happen to see ND too. I am assuming it is Notice Date. Can anyone tell me what for is this ND? How soon can we expect after RD. Any approximate time?

ANYWHERE FROM 3 WEEKS TO 3 MONTHS.

I am assuming next step is FP notice.

IF EVERYTHING OKAY, U CAN EXPECT FP NOTICE WITHIN FEW MONTHS.

I have a scar on my right thumb where the finger print is. The scar covers the finger partially. Do you think it is going to be a problem? Is there any alternative for that. Can we use another finger?

I DON'T THINK THIS WILL BE A PROBLEM.

If any RFEs are issued for all the above 4 applications or FP or medical we have to send the evidence right.

THIS IS CORRECT.

Then finally wait for EAD, AP, I 140, I 485 approvals.
If EAD is not approved have to go and get it on 91st day in SJ office as I live there.

NOW-A-DAYS U SHOULD GET EAD WITHIN 2 MONTHS. BUT YES, YOU CAN GOTO LOCAL INS AFTER 3 MONTHS.

Is this the process going to take place in GC from now on.

I am assuming inital steps are to note the RD and ND dates right.
Are any case numbers issued to all the 4 applications for tracking.

THIS IS NORMAL PROCESS. BUT IF YOU ARE LUCKY, YOU CAN BE PART OF PILOT PROGRAM AND CAN RECEIVE ALL APPROVALS WITHIN FEW MONTHS.
IF YOU GET YOUR FP NOTICE, BUT DON'T RECEIVE EAD/AP APPROVALS...YOU MAY BE PART OF PILOT PROGRAM. THEY DON'T APPROVE EAD/AP..DIRECTLY 485 AND BINGO..YOU GET UR GC....
 
scan some cases

Hi All,
did some scanning on wac03231 cases..no surprise...only one case had different status than received.

WAC03231XXXXX Received 8/8/2003
WAC03231XXXXX Received 8/8/2003
WAC03231XXXXX Received 8/8/2003
WAC03231XXXXX Received 8/8/2003
WAC03231XXXXX Received 8/8/2003
WAC03231XXXXX Received 8/8/2003
WAC03231XXXXX Received 8/8/2003
WAC03231XXXXX Received 8/8/2003
WAC03231XXXXX RFE recvd 2/12/2004

maybe we should scan some cases between 7/18/03 and 7/31/03...b4 jumping to august cases.
 
Hi, I am new to this site. Can someone tell me where to get case # that filed around the same time as I did. My RD is 8/1/03. Thanks!

PhDchemist said:
Hi all,

I've been scanning some 58 I-140 cases submitted in mid-September 2003 (as my case is). Here are the cases where status changed from recieved:

RFE sent on 6/19/2004
Approved on 6/21/2004
RFE recvd on 3/25/2004
Approved on 5/12/2004
RFE sent on 6/19/2004
RFE sent on 12/27/2003
RFE sent on 6/19/2004
RFE recvd on 4/16/2004
Approved on 6/21/2004
Approved on 6/2/2004

Since most of these were touched/approved in June 04 it seems that things are moving (slowly of course;-))
 
ultrascan said:
Hi, I am new to this site. Can someone tell me where to get case # that filed around the same time as I did. My RD is 8/1/03. Thanks!

Hi ultrascan, I've been doing some scanning and this is what I discovered. WAC number consists of 2 digits of fiscal year (WAC03) then the day of the fiscal year when application was recieved: mine was 09/24 (265 day of 2003 fiscal year - WAC03265) then I think (not sure about this) all applications have 5 in CSC (WAC032655) and then serial number. I just scan all numbers and find I-140 cases. Tedious job, but the only was of finding out the status as far as I know. Post something when you find out. As far as cases filed in late Sep 2003 - no change in last couple of weeks. :cool:
 
PhDchemist,

Thanks for the trick. I will try to do some scan myself. I filed in early August, when it tooks about 2 weeks to get I140 approved. But it all went wrong afterwards. As we observed, it only move by 1 day in the last 12 months.
 
Is it true?

PhDchemist said:
Hi ultrascan, I've been doing some scanning and this is what I discovered. WAC number consists of 2 digits of fiscal year (WAC03) then the day of the fiscal year when application was recieved: mine was 09/24 (265 day of 2003 fiscal year - WAC03265) then I think (not sure about this) all applications have 5 in CSC (WAC032655) and then serial number. I just scan all numbers and find I-140 cases. Tedious job, but the only was of finding out the status as far as I know. Post something when you find out. As far as cases filed in late Sep 2003 - no change in last couple of weeks. :cool:

mmigrationwatch.com
WAC030725**** 01/02/03 APPROVED 07/09/04 RFE_RCVD 10/17/03
WAC031305**** 03/19/03 APPROVED 07/17/04 RECEIVED_0 03/19/03
WAC031555**** 04/23/03 APPROVED 07/15/04 RECEIVED_0 04/23/03
WAC031715**** 05/15/03 APPROVED 07/17/04 RECEIVED_0 05/15/03
WAC031775**** 05/23/03 APPROVED 07/06/04 RECEIVED_0 05/23/03
WAC031795**** 05/28/03 APPROVED 07/14/04 RECEIVED_0 05/28/03
WAC031805**** 05/29/03 APPROVED 07/17/04 RFE_RCVD 05/03/04
WAC031845**** 06/04/03 APPROVED 07/07/04 RFE_RCVD 03/12/04
WAC031915**** 06/13/03 APPROVED 07/09/04 RECEIVED_0 06/13/03
WAC031945**** 06/18/03 APPROVED 07/12/04 RFE_SENT 04/16/04
WAC031955**** 06/19/03 APPROVED 07/08/04 RECEIVED_0 06/19/03
WAC031965**** 06/20/03 APPROVED 07/14/04 RECEIVED_0 06/20/03
WAC031985**** 06/24/03 APPROVED 07/12/04 RECEIVED_0 06/24/03
WAC031985**** 06/24/03 APPROVED 07/12/04 RECEIVED_0 06/24/03
WAC031995**** 06/25/03 APPROVED 07/16/04 RECEIVED_0 06/25/03
WAC032005**** 06/26/03 APPROVED 07/08/04 RECEIVED_0 06/26/03
WAC032005**** 06/26/03 APPROVED 07/12/04 RECEIVED_0 06/26/03
WAC032025**** 06/30/03 APPROVED 07/08/04 RFE_RCVD 03/23/04
WAC032035**** 07/01/03 APPROVED 07/09/04 RECEIVED_0 07/01/03
WAC032045**** 07/02/03 APPROVED 07/13/04 RECEIVED_0 07/02/03
WAC032115**** 07/14/03 APPROVED 07/15/04 RECEIVED_0 07/14/03
WAC032125**** 07/15/03 APPROVED 07/16/04 RECEIVED_0 07/15/03
WAC032285**** 08/05/03 APPROVED 07/16/04 RECEIVED_0 08/05/03
WAC032345**** 08/13/03 APPROVED 07/13/04 RFE_SENT 04/15/04
WAC032475**** 09/02/03 APPROVED 07/08/04 RECEIVED_0 09/02/03
WAC032485**** 09/03/03 APPROVED 07/13/04 RECEIVED_0 09/11/03
WAC032495**** 09/04/03 APPROVED 07/17/04 RECEIVED_0 09/04/03
WAC032535**** 09/09/03 APPROVED 07/15/04 RECEIVED_0 09/09/03
WAC032575**** 09/13/03 APPROVED 07/06/04 RECEIVED_0 09/13/03
WAC032635**** 09/22/03 APPROVED 07/19/04 RECEIVED_0 09/22/03
WAC032675**** 09/26/03 APPROVED 07/15/04 RECEIVED_0 09/26/03
WAC032685**** 09/29/03 APPROVED 07/08/04 RECEIVED_0 09/29/03
WAC032685**** 09/29/03 APPROVED 07/19/04 RECEIVED_0 09/29/03
WAC040535**** 12/17/03 APPROVED 07/12/04 RFE_RCVD 06/14/04
WAC040865**** 02/06/04 APPROVED 07/15/04 RFE_RCVD 06/08/04
WAC041335**** 04/09/04 APPROVED 07/13/04 RECEIVED_0 04/09/04
WAC041625**** 05/17/04 APPROVED 07/16/04 RECEIVED_0 05/17/04

Looks like they started to do some I-140 processing.
Am I dreaming?
 
140

i made a resolution that i won't check this site or USCIS site for processing dates or anything for a month. i am back after a month and not processing hasn't moved an inch. as i expected.

so is it true that they are processing sep '03 apps? mine says 360-360 days. it will be 360days in 6 weeks. damn..its so pathetic.

when i did (truly) concurrent filing last year, my wife was pregnant. so we couldn't do her full physical tests or shots. would that effect my app 140/485 in anyway?

thanks
 
CSC I-485 approved

Dear Friends,

I got email confirmation today about my I-485 approval.
My wife's and mine both got approved.
I am so glad that this journey has finally ended with good news.

Cant wait for the day when I will get my passport stamped and receive green card
in my hand.I am very happy today and wish other members good luck and best wishes.
i am sure you will get there.Just be patient. I know it is hard to be patient.

I had been reading posts on this group that they applied EAD or AP renewal and they got their I-485 approved.
I did same thing. Although, there was no need for me to get EAD renewed, I thought let me try if this will trigger
my I-485 approval.And it did.

I-140 filed 05/01/2003 with a substitute labor.
Pushed my company and paid myself to file I-485 08/22/2003 (I-140 still pending)
Filed amended I-140 in 10/01/2003.
RFE received for first I-140 02/01/2004. replied to RFE 02/15/2004.This I-140 got approved on 03/05/2004.
First EAD recd on 12/10/2004 and AP 11/12/2004.
Applied for EAD renewal 06/30/2004 and I-485 got approved

I thanks to all the members of this forum for their support.

God bless you all.
:)
 
Top