Originally posted by gingibi
vettipuls, you are correct!
I looked at a snapshot of data from the consolidated file (May 01 to Sep 01). If TSC keeps the current pace of approvals it looks like they will need about 80 more work days to finish the FY 2001.
Statistics for cases from beginning of May 01 to end of Sep 01
Total cases: 11959
Approved: 6055 (50.6%)
Transferred: 1381 (11.5%)
Remaining: 4523 (37.8%)
Approved in February (1 Feb-11 Feb): 452
Work days (1 Feb-11 Feb): 8
Current average rate of approval: 56 cases per day
Work days needed to finish the remaining cases: 80 (4 months)
The processing pattern in February clearly changed - they are now working cases for the whole period from May to Nov, while in January they were going only through May and Aug cases. It looks like their objective changed from trying to move the processing date further to trying to clear the whole pile of 2001 cases ASAP.