sunnysai said:I am happy and proud to say that my entire GC process is completed in 8months and 10days. Thanks guys for all your help and keeping this forum so lively. WISH YOU GOOD LUCK for your GC process.
Labour: 1month
I140 : 41days
I485 : 84days
Thanks,
Sunnysai
sunnysai said:Labour: 1month
I140 : 41days
I485 : 84days
indianexpert said:You should probably but Lotto Tickets as you will definately win
manoharTX said:Congratulations!.
Can you please post your ND/RD?
Thanks
indianexpert said:You should probably but Lotto Tickets as you will definately win
emailraja said:how is that possible?
what state are u in?
what category are u in?
what do u do?
who do you work for?
where can i send u my resume?
abc13 said:Congrats lucky!!!
As per my judgement, it took only 5 months and 2-3 days for your approval. Am I correct? how do you comeup with your numbers?
sunnysai said:Labor= ND: 04/01/04 AD:05/06/04
I140/485/EAD,AP= RD: 09/13/04 ND: 09/16/04
I140= AD: 10/27/04
RFE EAD/AP on 10/12/04 for photo
Responded to RFE on 10/28/04
EAD: AD 11/23/04
AP: LUD changed on 11/22/04 but no message change
FP = ND: 10/28/04 Done on: 11/03/04, LUD: 11/10/2004 FP received and process resumed, LUD 11/15/04 no change in message
485 : AD 12/10/04. I initiated the address change 12/06/04, not sure if this triggered the approval.
---Sunnysai