Below are my dates for concurrent filing.
140 - 05 Sept 2004
485 - 05 Sept 2004
RFE for 140 - 15 Jan 2005 Replied: Jan end (Do not know date since lawyer sent)
FP scheduled - March 2005.
I got an RFE for education evaluation. My lawyer said he replied RFE with a copy of education evaluation.
As per my knowledge whoever applied after April 30, 2004 they will get I-140 and 485 approval together.
My 140/485 dates are in Sept 04 means 140 will not be approved till 485 date is current? Do I get approval
for 140 before 485? I got finger print notice and scheduled on March 2005.
What is priority date? I do not see any where in my applications? We applied labor in Jan 2004. What is current priority dates going on.
I am EB3 category.
140 - 05 Sept 2004
485 - 05 Sept 2004
RFE for 140 - 15 Jan 2005 Replied: Jan end (Do not know date since lawyer sent)
FP scheduled - March 2005.
I got an RFE for education evaluation. My lawyer said he replied RFE with a copy of education evaluation.
As per my knowledge whoever applied after April 30, 2004 they will get I-140 and 485 approval together.
My 140/485 dates are in Sept 04 means 140 will not be approved till 485 date is current? Do I get approval
for 140 before 485? I got finger print notice and scheduled on March 2005.
What is priority date? I do not see any where in my applications? We applied labor in Jan 2004. What is current priority dates going on.
I am EB3 category.