Look at these similarities, they are hilarious ...
http://www.ncroads.com/interst/ih485.htm
When will it end? The original (pre-1998) target date for the completion of I-485 was 2008. However, due to late-1998 funding shortfalls and changes in the budgeting process, most of the project was forced back, especially those sections which had not started construction yet[3]. At the time, the state moved the completion date for all of 485 back to 2013.
In early 1999, many Charlotte politicians became willing to convert I-485 into a toll road in order to speed up construction. This idea was quickly dismissed, however, because Federal law prohibits states from tolling roads such as I-485 on which federal funds have already been spent[4].
In January 2001, the state announced some good news for 485: it was now planning to speed up construction of 485, so that the entire freeway could be finished by 2010, three years ahead of the 1998 schedule. This was made possible partly because freeway projects in other parts of the state were being held up, making more money for available sooner for 485