Got my 485 done. Timeline:
LC PD : April 12, 2002
State: CT
DOL: Boston
Issue(s): Missing Prevailing wage statement with LC.
Effect: LC approval delayed by almost 3 months.
SESA Done: Jan 25, 2004
DOL Done: Feb 17, 2004
140/485/EAD/AP Applied: March 24, 2004
RD: April 08, 2004
ND: April 15, 2004
Category: EB2
EAD/AP approved: July 01, 2004 Valid till July 04, 2005
FP Notice recd: Feb 23, 2005.
Code: 3
FP done: Feb 24, 2005(Early FP), scheduled April 15, 2005 in Newark.
140 Approved: Mar 21, 2005.
485 Approved: Mar 21, 2005.
Card Ordered: Mar 21, 2005.
Thanks everyone.
Got my 485 done. Timeline:
LC PD : April 12, 2002
State: CT
DOL: Boston
Issue(s): Missing Prevailing wage statement with LC.
Effect: LC approval delayed by almost 3 months.
SESA Done: Jan 25, 2004
DOL Done: Feb 17, 2004
140/485/EAD/AP Applied: March 24, 2004
RD: April 08, 2004
ND: April 15, 2004
Category: EB2
EAD/AP approved: July 01, 2004 Valid till July 04, 2005
FP Notice recd: Feb 23, 2005.
Code: 3
FP done: Feb 24, 2005(Early FP), scheduled April 15, 2005 in Newark.
140 Approved: Mar 21, 2005.
485 Approved: Mar 21, 2005.
Card Ordered: Mar 21, 2005.